SUMMARY


The Jordan Basin Improvement District is seeking proposals from qualified integrators to transition from existing GE iFIX SCADA software to Inductive Automation’s Ignition SCADA software.
Settle Signals

RFP Hunter shows what’s open. Settle shows what’s forming.

Deals like this one start months before the RFP. Settle reads the signals first, so your team is talking to Jordan Basin Improvement District while competitors are still waiting for the posting.

How an RFP like this forms

  1. Budget approved

    Settle flags it

    Board minutes and budget documents

  2. Scope and vendors researched

    Settle flags it

    Planning documents, meeting agendas, contract renewals

  3. RFP posted

    You are here

    Every bidder can see it now

Learn more about Settle

DESCRIPTION


The Jordan Basin Improvement District is requesting proposals from qualified integrators to transition from existing GE iFIX SCADA software to Inductive Automation’s Ignition SCADA software for the operation of the Jordan Basin Water Reclamation Facility and District-owned lift stations. The project includes integration of the current iFIX database, building screens and navigation in Ignition, configuring alarms and callout systems, building the Ignition database, and providing training and support to District staff. The integration must be completed no later than November 30, 2027. The contract term is from January 1, 2027, through December 31, 2027, with potential annual renewals not to exceed five years.

KEY REQUIREMENTS


  • Must have at least two integrators with Gold level Ignition certification
  • Must have a physical office along the Wasatch Front
  • Must have at least two integrators centered out of the local Utah office
  • Must provide three project references of full system integration of Inductive Automation’s Ignition SCADA software for wastewater applications
  • Must provide one project reference of integrating from GE iFIX to Ignition SCADA software

Do you qualify? Get a free fit score and answer these once for every RFP that asks.

TIMELINE


Post Notice & Invitation to Bid: November 2nd, 2026

Bid Inquiries: December 4th, 2026

Bid Deadline and Opening: December 10th, 2026

Contract Start: January 1st, 2027

Contract Completion: December 31st, 2027

Issuing Agency


Jordan Basin Improvement District

Organization overview and procurement intelligence available on paid plans.
See Issuer Research

Similar RFPs


Frequently asked questions


When is the submission deadline?
Submissions are due December 10, 2026. Questions must be submitted by December 4, 2026.
What is the budget for this RFP?
Settle estimates the budget at $150,000 – $300,000. The issuer has not published an official figure.
Who issued this RFP?
It was issued by Jordan Basin Improvement District. The work is located in Riverton, Utah, United States.

Analysis generated by Settle AI from the source RFP.

RFP Hunter shows what is open. Settle shows what is forming.

Settle pieces together buyer signals, budgets, contract activity, and the sources your team already monitors. See why an opportunity fits and what to do before the RFP posts.

See how Settle works