Mandatory pre-bid conference: May 20th, 2026.
Mandatory site visit: May 14th, 2026.
Question deadline: July 23rd, 2026.
Office access: October 1st, 2026.
Warehouse access: November 30th, 2026.
Substantial completion date: March 26th, 2027.
Primary procurement contact — name, title, email, and phone
Additional decision-makers and their departments
Alabama Department Of Finance, Division Of Procurement
The government authority in Montgomery, Alabama is seeking a contractor to provide surrender obligation general contractor services for a warehouse and associated office areas. The work involves removal, restoration, cleaning, and disposal activities needed to return the facility in accordance with surrender requirements.
Scope of work includes removal of warehouse fixtures, shelving, racking, conveyors, fencing, equipment, and warehouse office components. The contractor will also remove electrical, low-voltage, and exposed systems; perform plumbing-related work; address overhead, roll-up, and passage doors; and remove the mini-split HVAC unit located in the camera room.
Additional requirements include office area restoration such as ceiling grid, floor, and wall repairs; parking lot repair; building cleaning; debris removal; filling and cleaning the warehouse floor; pressure washing; and transportation and disposal of all removed materials.