Mandatory Information Session: June 30th, 2026
Questions due by: July 2nd, 2026
Responses to questions available: July 7th, 2026
Proposal submission deadline: July 14th, 2026
Removal and storage of solar panels: Mid July 2026
Roof completion estimate: Mid August 2026
Reinstallation: 90 days from removal date, estimated by end of September 2026
Primary procurement contact — name, title, email, and phone
Additional decision-makers and their departments
City Of Waterbury
The government authority located in Waterbury, Connecticut is seeking qualified vendors to provide comprehensive solar panel removal and reinstallation services. The contractor is responsible for safely shutting down the existing system, ensuring the work area is secure, and properly disconnecting all components in preparation for removal.
Solar panels must be carefully removed, labeled, and organized for storage in a secure, locking storage tank provided by the contractor, located in the adjacent parking lot for up to 90 days. In addition to the panels, all mounting hardware, including rails, feet, and related attachments, must also be removed and securely stored.
After the completion of roof replacement by the designated roofing company, the contractor will be required to begin reinstallation of the solar panels, ensuring that each panel is correctly aligned, securely attached, and properly spaced. The full contract period will last one year. Vendors must submit all questions regarding this RFP by July 2, 2026.