RFP Issued: September 1st, 2026
Pre-Proposal Meeting & Site Visit: September 11th, 2026
Engineering Proposals Due: September 24th, 2026
Engineering Contract Issued: November, 2026
30% Design Submittal: February, 2027
60% Design Submittal: April, 2027
90% Design Submittal: July, 2027
Design Complete: August, 2027
Advertise for Bids: August, 2027
Award Contract: October, 2027
Construction Complete: April, 2029
Primary procurement contact — name, title, email, and phone
Additional decision-makers and their departments
Lexington-Fayette Urban County Government
A government authority in Lexington, Kentucky is seeking a qualified vendor to provide design services. The required scope includes preliminary design and field evaluation, final design, easement acquisition, services during bidding, and resident observation services.
All questions regarding the opportunity must be submitted no later than September 15, 2026. Proposals are due by September 24, 2026.