BOS Approval for CMAR RFQ Advertising: January 13th, 2026
Advertise/Release RFQ: January 15th, 2026
Optional Pre-Proposal Conference: January 27th, 2026
All Final Questions due: February 27th, 2026
Final Answered Questions posted: March 16th, 2026
Statement of Qualifications (SOQ) due: March 30th, 2026
RFQ SOQ's Review Period: April 1st, 2026 – April 8th, 2026
Interview Reservations (Tentative): April 9th, 2026 – April 15th, 2026
SCDA Review/ Approval of BOS package: April 16th, 2026 – April 23rd, 2026
Tentative date to Send Notifications of Intent to Award: TBD
Preconstruction Negotiations: June 1st, 2026 – June 12th, 2026
Projected Board of Supervisors Approval of the Selection of a CMAR: June 16th, 2026
Projected Preconstruction Services Notice to Proceed: June 30th, 2026
Phased Construction Start: August 3rd, 2026
All phased Construction completed no later than: March 15th, 2027
Project Operational Turn Over: April 12th, 2027
Primary procurement contact — name, title, email, and phone
Additional decision-makers and their departments
County of Sacramento
A government authority in California is seeking an experienced Construction Manager at Risk to oversee various aspects of a significant construction project. The selected construction manager will be responsible for providing recommendations on construction feasibility, addressing potential labor or material shortages, managing procurement timelines, installation processes, and overseeing construction to completion. Responsibilities include providing detailed cost estimates, evaluating alternative designs or materials, and developing preliminary budgets while considering relevant economic factors.
The construction manager will also conduct continuous in-progress reviews of design documents, commonly referred to in the industry as Schematic Design, Design Development, and Construction Documents. Consultation and advice are expected concerning construction feasibility, document clarity, completeness, constructability, and the coordination of trades and materials. The provider must also monitor the availability of trades, subcontractors, and materials, and offer input on alternate options as needed. Additionally, the construction manager is tasked with preparing, monitoring, and managing the project schedule throughout preconstruction, bidding, construction, commissioning, and close-out phases of the project.
A pre-bid meeting is scheduled for January 27, 2026, and all questions related to the project must be submitted by February 27, 2026.