See More RFPs

Johnson County Wastewater

Brush Creek Pump Station Improvements Project

Due
Dec 9, 2026
Questions due
Nov 25, 2026
Budget
$12,000,000 – $17,000,000
Verified
Location
  • Olathe, Kansas, United States
Posted
Nov 4, 2026

SUMMARY


Johnson County Wastewater is seeking a design-build team to provide preconstruction, design, and construction services for the Brush Creek Pump Station Improvements project.
Settle Signals

RFP Hunter shows what’s open. Settle shows what’s forming.

Deals like this one start months before the RFP. Settle reads the signals first, so your team is talking to Johnson County Wastewater while competitors are still waiting for the posting.

How an RFP like this forms

  1. Budget approved

    Settle flags it

    Board minutes and budget documents

  2. Scope and vendors researched

    Settle flags it

    Planning documents, meeting agendas, contract renewals

  3. RFP posted

    You are here

    Every bidder can see it now

Learn more about Settle

DESCRIPTION


Johnson County Wastewater (JCW) is procuring a Progressive Design-Build team for the Brush Creek Pump Station Improvements project (MTM1-C080). The project involves replacing the existing pump station, originally built in 1956, to address aging assets, code compliance, and future wet weather flow requirements. The scope includes preconstruction services, design, and construction. The estimated total project cost is between $12 million and $17 million. The contract term is effective upon execution and remains in force until project completion and final payment.

KEY REQUIREMENTS


  • Must be a legally registered entity authorized to conduct business in the State of Kansas
  • Must be a licensed contractor in Johnson County
  • Must have an experience modification rate (EMR) of not greater than 1.0 for the current and past two years
  • Must have the ability to secure performance and payment bonds up to $20 Million
  • Must have an A.M. Best Company Rating of A minus or better for surety and insurance providers
  • Must provide proof of registration with the Kansas Secretary of State if required by law
  • Must comply with minimum cyber security standards
  • Must comply with Level A and Level AA success criteria of WCAG 2.1 for digital content

Do you qualify? Get a free fit score and answer these once for every RFP that asks.

TIMELINE


Issue RFQ: November 4th, 2026

Virtual Non-Mandatory Pre-Selection Conference: November 12th, 2026

RFQ Clarification Deadline: November 25th, 2026

SOQ Submission Deadline: December 9th, 2026

Issue RFP to Shortlisted Firms: December 21st, 2026

Confidential Meetings and Site Visits: January 19th–20th, 2027

Proposal Deadline: February 5th, 2027

Interviews: February 22nd–26th, 2027

Notice of Intent to Award: March 2027

Contract Negotiations: March 12th–April 9th, 2027

Board Approval: April 16th–May 27th, 2027

Notice to Proceed: June 2027

Issuing Agency


Johnson County Wastewater

Organization overview and procurement intelligence available on paid plans.
See Issuer Research

CONTACTS


Primary procurement contact — name, title, email, and phone

Additional decision-makers and their departments

Similar RFPs


Frequently asked questions


When is the submission deadline?
Submissions are due December 9, 2026. Questions must be submitted by November 25, 2026.
What is the budget for this RFP?
The published budget is $12,000,000 – $17,000,000.
Who issued this RFP?
It was issued by Johnson County Wastewater. The work is located in Olathe, Kansas, United States.

Analysis generated by Settle AI from the source RFP.

RFP Hunter shows what is open. Settle shows what is forming.

Settle pieces together buyer signals, budgets, contract activity, and the sources your team already monitors. See why an opportunity fits and what to do before the RFP posts.

See how Settle works